Productivity Analysis in Concrete Building Construction

Year 2020, Volume: 25 Issue: 1, 391 - 404, 30.04.2020
https://doi.org/10.17482/uumfd.649299

Abstract

Unit Price Analysis of the Ministry of Environment and Urbanization is often used as a preferred resource in determining the approximate cost of construction and in preparing the work schedule. Within the scope of this study, man hour values 11 work items, which are widely used in construction of reinforced concrete buildings, are calculated by work measurement and related information was collected from subcontractors. Man hour values calculated as a result of work measurement and subcontractor experiences are compared with the Ministry of Environment and Urbanization unıt price analysis data. As a result of the study, it is concluded that the Ministry of Environment and Urbanization data should be revised according to current technology.

References

  • 1. Alboğa, Ö. (2019) Betonarme Binalarda İş Ölçümü ile Verimlilik Analizi Yapılması, Yüksek Lisans Tezi, Çukurova Üniversitesi.
  • 2. Aydın, M.K. (2019)http://www.mustafakemalaydin.com/wp-content/uploads/2014/08/Insaat_Projelerinde_Kalite_Yonetimi_Uygulamalari.pdf, Erişim tarihi: 15.08.2019, Konu: İnşaat Projelerinde Kalite Yönetimi Uygulamaları.
  • 3. Chuan,Q.T, Pheng,L.S. (2006)Enviromental Factors and Work Perfonmance of Project Managers in the Construction Industry, International Journal of Project Management, 24, 24-37. https://doi.org/10.1016/j.ijproman.2005.06.001
  • 4. Ghoddousi,P., Hosseini,M.R. (2012) A Survey Of The Factors Affectıng The Productivity Of Construction Projects in Iran, Technological And Economic Development of Economy, 18,1, 99–116. https://doi.org/10.3846/20294913.2012.661203
  • 5. https://portal.myk.gov.tr/index.php?option=com_meslek_std_taslak&view=taslak_listesi_yeni&msd=2, Erişim Tarihi:12.12.2019, Konu: Ulusal Meslek Standartları.
  • 6. http://disk.org.tr/wp-content/uploads/2019/02/DISK-AR-Krizde-Emeg%CC%86in-Durumu-Arastirmasi-SON.pdf , Erişim Tarihi: 18.12.2019, Konu: Krizde Emeği Durumu Araştırması.
  • 7. https://intes.org.tr/wp-content/uploads/2019/01/%C4%B0N%C5%9EAATSEKT%C3%96R%C3%9C-RAPORU.pdf , Erişim tarihi: 15.08.2019, Konu: İnşaat Sektörü Raporu (2019).
  • 8. http://intes.admind.com.tr/wp-content/uploads/2017/12/sayi_134.pdf, Erişim tarihi:16.08.2019, Konu: İnşaat Sanayi Dergisi, 2017 raporu.
  • 9. Ibroke,O.T., Oladinrin,T.O., Adeniyi,O., Eboreime,I.V. (2013) Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria Journal of Construction in Developing Countries, 18,1,53–72.
  • 10. Ikediashi,D.I., Ogunlana,S.O., Alotaibi,A. (2014) Analysis of Project Failure Factors for Infrastructure Projects in Saudi Arabia: A Multivariate Approach, Journal of Construction in Developing Countries, 19,1,35–52.
  • 11. Karim,N.A., Hassan,S.H., Yunus,J.N., Hashim,M.Z. (2012) Factors Influence Labour Productivity and the Impacts on Construction Industry, Awam International Conference on Civil Engineering &Geohazard Information Zonation.MALEZYA.
  • 12. Kazaz, A.,Ulubeyli, S. (2004) A different approach to construction labour in Turkey: comparative productivity analysis,Building and Environment,39,93 – 100. https://doi.org/10.1016/j.buildenv.2003.08.004
  • 13. Kobu, B. (1998) Üretim Yönetimi, Beta Yayınları, İstanbul.
  • 14. Kuruoğlu,M., Bayoğlu,F.İ. (2001)Yapı Üretiminde Adam saat Değerlerinin Belirlenmesi Üzerine Bir Araştırma Ve Sonuçları. XVI İnşaat Mühendisliği Teknik Kongresi. ANKARA.
  • 15. Olaoluwua,O., Adesanya,D.A. (2015) Productivity of Concrete Placement by Dumpers in Nigeria, International Journal of Engineering Research and Development ,11, 03,15-28. http://dx.doi.org/10.7492/IJAEC.2015.004
  • 16. Oral,E., Mıstıkoğlu,G., Tufan,D. (2006)Zaman Etüdü İle Yapım İşlerinde Adam Saat Değerlerinin Belirlenmesi.7.Uluslararası İnşaat Mühendisliğinde Gelişmeler Kongresi,İstanbul.
  • 17. Oral, M., Oral, E., Aydın, A. (2011) Supervised vs. Unsupervised Learning for Construction Crew Productivity Prediction,Automation in Construction,22,271-276.doi:10.1016/j.autcon.2011.09.002
  • 18. Öcal,M.E, Tat,A., Erdiş,E. (2005) Bayındırlık İşleri Birim Fiyat Analizlerindeki İşgücü Verimliliklerinin İncelenmesi.3.Yapı Kongresi,İzmir.
  • 19. REFA. (1985) İş Etüdü ve Yöntem Bilgisi. Cilt:1-2-3, MPM Yayınları, Yayın no: 544, Ankara.
  • 20. Shehata,M.E., El-Gohary,K.M. (2011) Towards improving construction labor productivity and projects’ performance,Alexandria Engineering Journal,50,321–330. doi:10.1016/j.aej.2012.02.001
  • 21. Tat, A. (2000) Bayındırlık İşleri Birim Fiyat Analizlerindeki İşgücü ve Makine Gücü Verimliliklerinin İrdelenmesi, Yüksek Lisans Tezi, Çukurova Üniversitesi.
  • 22. Tufan, D. (2007) Bina İnşaatlarında Adam Saat Değerlerinin Belirlenmesi Üzerine Bir Uygulama Örneği, Yüksek Lisans Tezi, Mustafa Kemal Üniversitesi.
  • 23. Ulubeyli, S., Kazaz, A., Er, B. (2014) Planning Engineers’ Estimates on Labor Productivity: Theory and Practice, Procedia- Social and Behavioral Sciences, 119 ,12 – 19. https://doi.org/10.1016/j.sbspro.2014.03.004

BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ

Year 2020, Volume: 25 Issue: 1, 391 - 404, 30.04.2020
https://doi.org/10.17482/uumfd.649299

Abstract

İnşaat sektöründe yapı yaklaşık maliyeti belirlenirken ve iş programı hazırlanırken pratik olması amacıyla Çevre ve Şehircilik Bakanlığı’na ait Birim Fiyat Analizleri sıklıkla tercih edilen bir kaynak olarak kullanılmaktadır. Bu çalışma kapsamında betonarme bina inşaatlarında yaygın olarak kullanılan 11 adet iş kaleminin iş ölçüm yöntemi ile adam saat değerleri hesaplanmış ve bu çalışmaya ek olarak taşeronlardan deneyimlerine bağlı olarak adam saat değerleri ile ilgili bilgi toplanmıştır. İş ölçümü ve taşeron deneyimleri sonucu hesaplanan işgücü verimlilikleri Çevre ve Şehircilik Bakanlığı verileri ile karşılaştırılmıştır. Çalışma sonucunda, Çevre ve Şehircilik Bakanlığı verilerinin güncel teknolojiye göre revize edilmesi gerektiği sonucuna ulaşılmıştır.

References

  • 1. Alboğa, Ö. (2019) Betonarme Binalarda İş Ölçümü ile Verimlilik Analizi Yapılması, Yüksek Lisans Tezi, Çukurova Üniversitesi.
  • 2. Aydın, M.K. (2019)http://www.mustafakemalaydin.com/wp-content/uploads/2014/08/Insaat_Projelerinde_Kalite_Yonetimi_Uygulamalari.pdf, Erişim tarihi: 15.08.2019, Konu: İnşaat Projelerinde Kalite Yönetimi Uygulamaları.
  • 3. Chuan,Q.T, Pheng,L.S. (2006)Enviromental Factors and Work Perfonmance of Project Managers in the Construction Industry, International Journal of Project Management, 24, 24-37. https://doi.org/10.1016/j.ijproman.2005.06.001
  • 4. Ghoddousi,P., Hosseini,M.R. (2012) A Survey Of The Factors Affectıng The Productivity Of Construction Projects in Iran, Technological And Economic Development of Economy, 18,1, 99–116. https://doi.org/10.3846/20294913.2012.661203
  • 5. https://portal.myk.gov.tr/index.php?option=com_meslek_std_taslak&view=taslak_listesi_yeni&msd=2, Erişim Tarihi:12.12.2019, Konu: Ulusal Meslek Standartları.
  • 6. http://disk.org.tr/wp-content/uploads/2019/02/DISK-AR-Krizde-Emeg%CC%86in-Durumu-Arastirmasi-SON.pdf , Erişim Tarihi: 18.12.2019, Konu: Krizde Emeği Durumu Araştırması.
  • 7. https://intes.org.tr/wp-content/uploads/2019/01/%C4%B0N%C5%9EAATSEKT%C3%96R%C3%9C-RAPORU.pdf , Erişim tarihi: 15.08.2019, Konu: İnşaat Sektörü Raporu (2019).
  • 8. http://intes.admind.com.tr/wp-content/uploads/2017/12/sayi_134.pdf, Erişim tarihi:16.08.2019, Konu: İnşaat Sanayi Dergisi, 2017 raporu.
  • 9. Ibroke,O.T., Oladinrin,T.O., Adeniyi,O., Eboreime,I.V. (2013) Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria Journal of Construction in Developing Countries, 18,1,53–72.
  • 10. Ikediashi,D.I., Ogunlana,S.O., Alotaibi,A. (2014) Analysis of Project Failure Factors for Infrastructure Projects in Saudi Arabia: A Multivariate Approach, Journal of Construction in Developing Countries, 19,1,35–52.
  • 11. Karim,N.A., Hassan,S.H., Yunus,J.N., Hashim,M.Z. (2012) Factors Influence Labour Productivity and the Impacts on Construction Industry, Awam International Conference on Civil Engineering &Geohazard Information Zonation.MALEZYA.
  • 12. Kazaz, A.,Ulubeyli, S. (2004) A different approach to construction labour in Turkey: comparative productivity analysis,Building and Environment,39,93 – 100. https://doi.org/10.1016/j.buildenv.2003.08.004
  • 13. Kobu, B. (1998) Üretim Yönetimi, Beta Yayınları, İstanbul.
  • 14. Kuruoğlu,M., Bayoğlu,F.İ. (2001)Yapı Üretiminde Adam saat Değerlerinin Belirlenmesi Üzerine Bir Araştırma Ve Sonuçları. XVI İnşaat Mühendisliği Teknik Kongresi. ANKARA.
  • 15. Olaoluwua,O., Adesanya,D.A. (2015) Productivity of Concrete Placement by Dumpers in Nigeria, International Journal of Engineering Research and Development ,11, 03,15-28. http://dx.doi.org/10.7492/IJAEC.2015.004
  • 16. Oral,E., Mıstıkoğlu,G., Tufan,D. (2006)Zaman Etüdü İle Yapım İşlerinde Adam Saat Değerlerinin Belirlenmesi.7.Uluslararası İnşaat Mühendisliğinde Gelişmeler Kongresi,İstanbul.
  • 17. Oral, M., Oral, E., Aydın, A. (2011) Supervised vs. Unsupervised Learning for Construction Crew Productivity Prediction,Automation in Construction,22,271-276.doi:10.1016/j.autcon.2011.09.002
  • 18. Öcal,M.E, Tat,A., Erdiş,E. (2005) Bayındırlık İşleri Birim Fiyat Analizlerindeki İşgücü Verimliliklerinin İncelenmesi.3.Yapı Kongresi,İzmir.
  • 19. REFA. (1985) İş Etüdü ve Yöntem Bilgisi. Cilt:1-2-3, MPM Yayınları, Yayın no: 544, Ankara.
  • 20. Shehata,M.E., El-Gohary,K.M. (2011) Towards improving construction labor productivity and projects’ performance,Alexandria Engineering Journal,50,321–330. doi:10.1016/j.aej.2012.02.001
  • 21. Tat, A. (2000) Bayındırlık İşleri Birim Fiyat Analizlerindeki İşgücü ve Makine Gücü Verimliliklerinin İrdelenmesi, Yüksek Lisans Tezi, Çukurova Üniversitesi.
  • 22. Tufan, D. (2007) Bina İnşaatlarında Adam Saat Değerlerinin Belirlenmesi Üzerine Bir Uygulama Örneği, Yüksek Lisans Tezi, Mustafa Kemal Üniversitesi.
  • 23. Ulubeyli, S., Kazaz, A., Er, B. (2014) Planning Engineers’ Estimates on Labor Productivity: Theory and Practice, Procedia- Social and Behavioral Sciences, 119 ,12 – 19. https://doi.org/10.1016/j.sbspro.2014.03.004
There are 23 citations in total.

Details

Primary Language Turkish
Subjects Civil Engineering
Journal Section Research Articles
Authors

Özge Alboğa 0000-0002-2848-8373

Gözde Tantekin Çelik 0000-0002-0045-4489

Publication Date April 30, 2020
Submission Date November 20, 2019
Acceptance Date January 25, 2020
Published in Issue Year 2020 Volume: 25 Issue: 1

Cite

APA Alboğa, Ö., & Tantekin Çelik, G. (2020). BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ. Uludağ Üniversitesi Mühendislik Fakültesi Dergisi, 25(1), 391-404. https://doi.org/10.17482/uumfd.649299
AMA Alboğa Ö, Tantekin Çelik G. BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ. UUJFE. April 2020;25(1):391-404. doi:10.17482/uumfd.649299
Chicago Alboğa, Özge, and Gözde Tantekin Çelik. “BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ”. Uludağ Üniversitesi Mühendislik Fakültesi Dergisi 25, no. 1 (April 2020): 391-404. https://doi.org/10.17482/uumfd.649299.
EndNote Alboğa Ö, Tantekin Çelik G (April 1, 2020) BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ. Uludağ Üniversitesi Mühendislik Fakültesi Dergisi 25 1 391–404.
IEEE Ö. Alboğa and G. Tantekin Çelik, “BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ”, UUJFE, vol. 25, no. 1, pp. 391–404, 2020, doi: 10.17482/uumfd.649299.
ISNAD Alboğa, Özge - Tantekin Çelik, Gözde. “BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ”. Uludağ Üniversitesi Mühendislik Fakültesi Dergisi 25/1 (April 2020), 391-404. https://doi.org/10.17482/uumfd.649299.
JAMA Alboğa Ö, Tantekin Çelik G. BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ. UUJFE. 2020;25:391–404.
MLA Alboğa, Özge and Gözde Tantekin Çelik. “BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ”. Uludağ Üniversitesi Mühendislik Fakültesi Dergisi, vol. 25, no. 1, 2020, pp. 391-04, doi:10.17482/uumfd.649299.
Vancouver Alboğa Ö, Tantekin Çelik G. BETONARME BİNA İNŞAATLARINDA VERİMLİLİK ANALİZİ. UUJFE. 2020;25(1):391-404.

Announcements:

30.03.2021-Beginning with our April 2021 (26/1) issue, in accordance with the new criteria of TR-Dizin, the Declaration of Conflict of Interest and the Declaration of Author Contribution forms fulfilled and signed by all authors are required as well as the Copyright form during the initial submission of the manuscript. Furthermore two new sections, i.e. ‘Conflict of Interest’ and ‘Author Contribution’, should be added to the manuscript. Links of those forms that should be submitted with the initial manuscript can be found in our 'Author Guidelines' and 'Submission Procedure' pages. The manuscript template is also updated. For articles reviewed and accepted for publication in our 2021 and ongoing issues and for articles currently under review process, those forms should also be fulfilled, signed and uploaded to the system by authors.